Data Center, Munic, Thermal Storage, NorthC

Largest opera house of Berlin saves 36% energy costs by energy performance contract with guaranteed savings
Two Data Centers, Nuremberg / Munich, NorthC

NorthC is a data center operator with sites across Germany, the Netherlands, and Switzerland. The company runs its facilities on 100 % green energy, pursues carbon neutrality by 2030, and invests in innovative solutions such as residual heat recovery and green hydrogen systems to enhance sustainability. At NorthC’s data centers in Nuremberg and Munich, an […]
Automotive Production Site, Berlin

Comprehensive efficiency analysis for Visteon Factory At the time when the Berlin plant was still part of the Visteon Group, an in-depth energy audit was conducted to identify efficiency potentials across the entire automotive production site. The audit covered energy generation and distribution systems (heating, electricity, compressed air), HVAC installations, process cooling, lighting, drives, and […]
Deutsche Oper Berlin

Largest opera house of Berlin saves 36% energy costs by energy performance contract with guaranteed savings
Coffee Rostery, Berlin

Excerpt WH
q.Beyond AG, Germany

q.Beyond AG, a leading German IT service provider with over 1,100 employees and multiple high-security data centers, aims to reduce its overall emissions by at least 60% by 2027 compared to 2019 levels. We conducted a comprehensive Energy Audit in accordance with EN 16247 across all data centers and branch offices, describing key measures to […]
Data Center, q.Beyond AG, Hamburg

Asset & Context q.beyond AG operates german-wide high-availability data centers providing critical digital infrastructure services. As energy-intensive assets with continuously rising cooling demand, data centers face increasing pressure to reduce energy consumption, operating costs, and carbon emissions while maintaining maximum reliability. In 2024, one of q.beyond’s major data center sites in Hamburg required a targeted […]
Townhouse Quarter Prenzlauer Gärten, Berlin

Largest opera house of Berlin saves 36% energy costs by energy performance contract with guaranteed savings
Headquarter Production Site of Danfoss Group, Nordborg

https://youtu.be/kG8cFQGwmDE?si=mDzfIcaMwhwg1gnN In 2022, the 250,000 m² Nordborg factory site reached carbon neutrality. See how it works. Danfoss, one of Denmark’s largest industrial companies, develops solutions that improve machine productivity, reduce emissions, lower energy consumption, and enable electrification. In 2022, the company’s 250,000 m² Nordborg factory site achieved carbon neutrality in Scope 1 and Scope […]